The fit-out of the 650 rooms and public areas of nhow Amsterdam RAI hotel was completed just over a year ago, without a single delay. The operation was carried out with almost military precision under the leadership of INTERIOR-CONSULT, the Haarlem-based design studio responsible for the overall procurement and coordination of the interior fit-out of Europe’s largest hotel designed by OMA.

650 rooms at nhow Amsterdam RAI hotel

“It was fantastic to be part of this landmark project on Amsterdam’s ring road,” says owner and director Edzo Bosma. “It was a huge project, and looking back, you can say it went smoothly. Once the wheels are turning, everything falls into place. What has been achieved here is really impressive, truly unique.”

kopie-van-nhow3-receptie-op-1ste-verdieping-kopieren

Reception on the first floor.

INTERIOR-CONSULT specialises in the design and build of interiors for hotels, resorts and holiday parks, among others. Bosma: “For this NH hotel, our work involved design support, tendering for products and services, project preparation, contracting suppliers, budget control, planning and coordinating temporary storage, and the delivery and installation of all goods. For this project, we had to place orders with around 250 suppliers, covering some 1,000 different products. These included box-spring beds, armchairs, wardrobes, safes, minibars, lighting, curtains, signage, kitchens, buffets, cold rooms, reception furniture and a video wall, as well as plants and styling. We had to make sure the budget was not exceeded. We monitored the entire administration, from invoicing through to payment. In this way, we took the burden off our clients.”

A supporting role

The first discussions with the clients, developer COD and NH Hotels, took place at the end of 2017. “We really got started on delivering the project in April 2018,” says José Bontenbal, projects & procurement coordinator.

“Thorough preparation and a highly disciplined approach are essential. We need all the information on production times, logistics, installation times and handover dates. The interiors featured standard products as well as specially designed elements. We played a supporting role, for example translating the design into practical requirements and checking whether it could actually be implemented. This led, among other things, to changes to the electrical services in the rooms. We also checked whether upholstery fabrics were safe and durable enough for hotel use. We could make corrections when needed, because we knew the potential pitfalls in the designs.”

kopie-van-nhow1-kopieren

One of the murals at nhow Amsterdam RAI hotel. (Image: Infra Communicatie)

A striking feature of the interior was the large-scale murals at the heart of the hotel, visible from outside thanks to the glass façades. Bosma: “They are very prominent, combining street art and fine art. It wasn’t clear how they could be painted on the exposed concrete walls, so we brought in a mural artist from Zeeland who could do the job. Barre Verkerke is a true specialist in this field. His work turned out so well that he was also commissioned to paint a wall in the restaurant on the seventeenth floor, to his own design.”

A surprising end result

Good communication with the hotel operator, developer and contractor is vital on a project of this kind, says Bosma. “We chaired the interior and FF&E meetings (Furniture, Fixtures and Equipment). We set priorities and monitored the entire project, so we could anticipate potential problems and work out how to solve them. To keep things moving, we also did some design work ourselves from time to time.”

kopie-van-nhow4-omloop-kopieren

Hotel walkway.

INTERIOR-CONSULT has a warehouse in Sassenheim where the goods were stored temporarily. There was no room for this at the construction site next to the RAI. Deliveries were made from Sassenheim to Amsterdam on a just-in-time basis, with two INTERIOR-CONSULT project managers on site to ensure that all the goods could be installed on schedule.

Bontenbal: “While they were still pouring concrete on the top floor, we were already fitting out the rooms downstairs. This meant we could complete one floor a week, including commissioning and checking the building services. The collaboration with main contractor Pleijsier Bouw was very satisfactory. As soon as they had finished, we moved in. Together, we were able to create something truly special here. The end result is, and remains, very surprising.”    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Advertisement

Follow Binnenwerk

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.